Total Float Calculations

1 reply [Last post]
Imran Malik
User offline. Last seen 6 years 34 weeks ago. Offline
Joined: 24 May 2004
Posts: 20
Groups: None
Dear all
I have no.of projects in one master project. Contractual dates are different for almost every project. While P3 calculates total float for the last project. How can i force p3 to calculate total float for every project when finish date is different for everyone. I tried to apply zero total float for last milestone of the individual project but it made zero and negative for projects finishing earlier. Please help

Replies

Ronald Winter
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
You need to add a Finish-no-later-than constraint to the last milestone of each project using that project’s required finish date. Good luck!