Primavera Project Planner - P3 Member for 22 years 10 months Member for 22 years 10 months Submitted by Ronald Winter on Tue, 2008-04-01 10:10 Permalink RE: Total Float Calculations You need to add a Finish-no-later-than constraint to the last milestone of each project using that projects required finish date. Good luck! Log in or register to post comments
Member for 22 years 10 months Member for 22 years 10 months Submitted by Ronald Winter on Tue, 2008-04-01 10:10 Permalink RE: Total Float Calculations You need to add a Finish-no-later-than constraint to the last milestone of each project using that projects required finish date. Good luck!
Member for
22 years 10 monthsRE: Total Float Calculations
You need to add a Finish-no-later-than constraint to the last milestone of each project using that projects required finish date. Good luck!