Resource/Cost Graphics

1 reply [Last post]
Lorenzo Tolentino
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 14 May 2007
Posts: 12
Groups: None
On the dialogue box for producing graphical reports it shows there the resource selection,content,date,format,titles..etc. Under the content tab, pls give me more detail description of what the "Divide by" field can do.On the Primavera manual it only says that..."Specify a number in the Divide By field to determine how P3 shows resource or cost values in the graphic"...Should i only used this field to reduce the number shown on the report or it has other usage or purpose? Tnx - renz

Replies

Ashraf Jahangeer
User offline. Last seen 8 years 23 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Hi Renz,

The Divide field is used for reducing the scale of the Y axis. Say for example the Total Cost is comming 100,00,000 $ and you want to show it into millions then you can use devide by 10,00,000. Now your scale will show 1 to 10.

Regards,

Ashraf