Planning Unit

5 replies [Last post]
Philip Richards
User offline. Last seen 15 years 26 weeks ago. Offline
Joined: 7 Jan 2004
Posts: 29
Groups: None
I am running a Programme in P3, with planning unit set to Hours.

Can anyone advise if it is possible to maintain the Planning Unit in Hours, dut display durations in Days, or better still Days/Hrs

Replies

Philip Jonker
User offline. Last seen 16 years 2 hours ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi Philip,

Charles is quite correct. The problem is you cannot have the best of both worlds. The normal thing to do is run the programme in days, dependant on the overall duration and type of project, and use manhours in the resources, it is the closest youget to thre optimum. The trick is using the right lags in the logic, ie for example where you have activities with durations of less than a day, use FS -1, to keep them in the same day, but resource them correctly.

Obviosly in shutdown or turnaround situations you need to plan by the hour.

Hope this helps
Charleston-Joseph...
User offline. Last seen 3 years 18 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hi,

Planning unit is hours maybe good for projects with short duration.

but for projects that last more than one year, maybe it is not advisable.

So determine first if it is really practical to use planning unit in hours.

Regards,

charlie
Steven Oliver
User offline. Last seen 12 years 1 week ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
What you could do is to create a text CDI.

Export this and your activity data to Excel, and format appropriately. Then import back to P3.

HTH

Raja Izat Raja Ib...
User offline. Last seen 13 years 27 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
Hi,
Suggestion use hourly much better.. cause once U change daily unit very difficult to change the unit in hour back. Only thing, when u use hour, takes time to click the button to find what time the work finish and waste time if it is not required. But in terms of accuracy, very good. Its depends to the schedule, is it meet the contract / client requirement.
Sukumaran Subaram...
User offline. Last seen 9 years 19 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Philip,

a) Create custom data items.
b) Use global change to modify the duration from hours to days.

Regards.