Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Baseline Lag

1 reply [Last post]
Radhakrishnan Gun...
User offline. Last seen 15 years 46 weeks ago. Offline
Joined: 12 Dec 2004
Posts: 8
Groups: None

Is it possible to display baseline activity lag in activity field using P3. Or how to know the changes made to sequences of current plan when compared to baseline plan with out any plugins.

Replies

Jaco Stadler
User offline. Last seen 17 years 50 weeks ago. Offline
Joined: 9 Sep 2004
Posts: 299
Groups: None
Format Column + Target 1 Total Float = Baseline Lag
To See Slippage Variance Target 1 Early / Late Finish