Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

job must finish by

3 replies [Last post]
Rafael Davila
User offline. Last seen 1 week 6 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Old discussion - Deleted.

Replies

Rafael Davila
User offline. Last seen 1 week 6 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Old discussion - Deleted.

Luca Basile
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
More over Your Client accepted to have in the scedule activities with constrains (like must finish, must start, early start or finish, etc ...).

In my experience they accept only in the interface milestone to compare with another milestone at the end of the "work package".

If for example You put a must start on 10 april for a pole installation, it mean is missing all the logic for the procurement and delivery of it.
MK TSE
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
I think it is the network architecture problem rather P3 problem. To indue a project must finish on, at least 2 level can be control and either one of them can perform: at project overview and/or to the last activity.

However, if both client and contractor are in different sub-projects and merge to a master project, there will be another story.