Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Adding New Activities to the Project

1 reply [Last post]
Ali Hamouda
User offline. Last seen 8 years 26 weeks ago. Offline
Joined: 3 Feb 2002
Posts: 109
Groups: None
Dear sirs, I am facing this Problem,any one have Idea would be apreciated. Our client suggest to Add new activties to the project,but with the condition not to change the original dates of the program. If there is a way for linking the new activites,but not to affect the existing one..is it possible?or at least to affect some of the activites not the hole project. Best Regards Ali ----------------------------------

Replies

Mohd Mahd
User offline. Last seen 16 years 44 weeks ago. Offline
Joined: 13 Jul 2001
Posts: 62
Groups: None
Hi Ali, i think u can add activities without affecting a project as long as u r away from its critical and long path activities. also the added activities' durations are less than total float (before adding) of the predeccessor / successor ones. keep in mind that (in most cases) some of the current existing activities will be changed. wishing it is of some help. Mohd