Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Cannot tell Contractor "Means and Methods", how do you say there schedule will not work for on time completion then?

6 replies [Last post]
John Reeves
User offline. Last seen 7 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Cannot tell Contractor "Means and Methods", how do you say there schedule will not work for on time completion then?

Replies

Jake Cyrus Zafra
User offline. Last seen 2 years 1 hour ago. Offline
Joined: 7 Jun 2021
Posts: 12
Groups: None

I would like to ask for a small favor and cooperation in answering the survey with construction experience; kindly click the link: https://forms.office.com/r/cCdqqTeYgS

Jake Cyrus Zafra
User offline. Last seen 2 years 1 hour ago. Offline
Joined: 7 Jun 2021
Posts: 12
Groups: None

I would like to ask for a small favor and cooperation in answering the survey with construction experience; kindly click the link: https://forms.office.com/r/cCdqqTeYgS

Trevor Rabey
User offline. Last seen 2 years 5 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None

If you have any reasonable objection to any aspect of a contractor's program, which so often is flawed, you should say something. Other people, such as the project owner, are relying on you to say something. The tired old argument about not being able to interfere with the contractor's ways and means is a disingenuous argument which I have seen adopted by architects. It amounts to an abrogation of their responsibility. If the contractor won't respond to polite and reasonable requests, suggestions and recommendations, maybe derision and sarcasm will be needed.

Most contractors' programs are not just slightly imperfect with some minor faults and flaws. Usually, they are just junk.

John Reeves
User offline. Last seen 7 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

I just did a project where the exterior masonry delayed the job because the lack of windows meant they couldn't get the humidity good to do the floors, and couldn't finish the drywall because the windows were not in etc.  Now, on a new project they want to put the masonry off as late as possible.  Sure if they come out with enormous forces it is different, but do not trust that happen.  Do you have to allow more risk because the contractor opts for more risk?  What if you care more about completion, most ld's are not high enough to put fear in contractors, plus they frequently are not enforced either way.

John Reeves
User offline. Last seen 7 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Doing a school project.  Just finished a school project just like it, the current project is starting work later than the previous which did not finish in time.  It is difficult to say that, "in theory" things might be different, but I doubt it - do not know how to legally say "there is now way you are going to make it."  When owners due punish contractors for being late, they kind of learn to simply be late and deal with it.  Owners let this happen because having enough bidders is a big problem, and in the end this saves them money in the bid process on later projects.

Peter Holroyd
User offline. Last seen 4 days 7 hours ago. Offline
Joined: 6 Jun 2005
Posts: 166

John,

schedule needs to be accompanied by a Basis of Schedule document outlining all major assumptions used in constructing the programme.

Also there should be a Construction Phase Plan (CPP) which sets out the construction methodology.

If it all hangs together then really it's the contractor's responsibility to finish on time by whatever means and methods he wants to use. After all he's gone through a pre-qual process, a tender process, a contract award process so what can go wrong!

 

Peter