progress vs completion date

Member for

21 years 10 months

Clear and thanks Rodel

Member for

19 years

Hi Moutaz,

If the progress is delay, it does not necessary mean that the completion date is being push out or go further unless the delay is coming from the critical path. If the critical path is affected then recovery is needed to come back from the original completion date such as re-sequence the activity or compressed the schedule by addressing the delay and de-risk the critical path. Sometimes it happened that the progress is ahead than plan but overall the schedule is delay because the critical path is being affected by other delayed activities. Investigate, review and analyse your schedule and check where and what is the cause of behind schedule? Is it on the critical path or non-critical activities? Is it the weighthing of the activities or productivity issue?