If the progress is delay, it does not necessary mean that the completion date is being push out or go further unless the delay is coming from the critical path. If the critical path is affected then recovery is needed to come back from the original completion date such as re-sequence the activity or compressed the schedule by addressing the delay and de-risk the critical path. Sometimes it happened that the progress is ahead than plan but overall the schedule is delay because the critical path is being affected by other delayed activities. Investigate, review and analyse your schedule and check where and what is the cause of behind schedule? Is it on the critical path or non-critical activities? Is it the weighthing of the activities or productivity issue?
Member for
21 years 10 monthsClear and thanks Rodel
Clear and thanks Rodel
Member for
19 yearsHi Moutaz,If the progress is
Hi Moutaz,
If the progress is delay, it does not necessary mean that the completion date is being push out or go further unless the delay is coming from the critical path. If the critical path is affected then recovery is needed to come back from the original completion date such as re-sequence the activity or compressed the schedule by addressing the delay and de-risk the critical path. Sometimes it happened that the progress is ahead than plan but overall the schedule is delay because the critical path is being affected by other delayed activities. Investigate, review and analyse your schedule and check where and what is the cause of behind schedule? Is it on the critical path or non-critical activities? Is it the weighthing of the activities or productivity issue?