EVA

Dear all

I have been asked to produce EVA in P6 on a residential project. I have prepared the schdule. How can i create ASAP &ALAP CURVES.

2. Should my QS give the rates for the works planned. But in residential projects for example I have shown Level 1 Brick Work - 2weeks. should this duration based on sqmtr/gang. 

3. iam confused because in apartment fitout, Electrical installation is for 2 weeks. how will assign cost for this.

need your help...

 

thanks

Ram

Z
Zoltan Palffy 👤 Member for 17 years

1. view show on bottom resource usage profile lower right are right click  resource usage profile options 

click units

for the ASAP curve click remaining early box

for the ALAP curve click the remaining late box

2. The durations should be as long as it takes based on the quantity of brick work to install divided by the production rate divided by the number of brick layers i.e. 1000 bricks to lay standard rate is 1 man 500 bricks per day

so 1000/500 = 2 days for 1 man or 1000/1000 = 1 day for 2 men 

3. whats the cost for the material ? whats the cost for the labor ?

material cost would be wire, panles and fixtures

labor cost would be manhours multimplied bty the labor rate 

total cost would be material + Labor

add an electrican resource and put the cost in as the total of the material and labor

Featured Partner

Top Posters

Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts
Patricio_aoa
0 posts
James Williams
75 posts
Philip Assou-Dodji
1 posts
jeoffrey reyes
15 posts
markg
0 posts
Manjeet Yadav
0 posts
Pan
0 posts