Contractor's Delay from 30 Oct 2016 to 30 April 2017
Client's Delay from 30 Jun 2016 to 30 Mar 2017.
Is it a concurrent delay?
if you hand draw this on paper it will be crystal clear
There are 2 parts attributal to the contractor delays. The Contractor Delay #1 is from June 30, 2016 to October 29,2016. The concurrent portion of the delay is from October 30, 2016 to March 30, 2017. The Contractor Delay #2 is from April 1, 2017 to April 30, 2017
Member for
16 years 3 monthsContractor's Delay from 30
Contractor's Delay from 30 Oct 2016 to 30 April 2017
Client's Delay from 30 Jun 2016 to 30 Mar 2017.
Is it a concurrent delay?
Member for
14 years 7 monthsHi Dimple,Ya it is Concurrent
Hi Dimple,
Ya it is Concurrent delay.
So you can apply LD for a Duration of Contractor Finish Date - Client Delay Impact Date = 30 April 17 - 30 Mar 17 = 30 Days.
Mike would be able to answer it much better.
Regards
Jithin