Store period performance

Dear Experts ,

When I checked our contractor's weekly and Monthly report , I found that each weekly and monthly period showing diffrent actual figures for the same month . I guess promavera just distribute the actuals over the period every time when it gets updated

My first question is - is this an reasonable reson to say that  data comes from P6 software ? or we have to do it manually to make sence ?

Second- Contrator is reluctant to use the option "Store period performance"  

your view please ?

Janaka

 

R
Raymund de Laza 👤 Member for 16 years 7 months

Actual Cost That was Auto Calculated by Primavera is a fancy Actual Cost. Actual Expenses is the Actual Cost supposed to be manually entered and it is supposed to be Saved periodically using the "Store Period performance".

 

Regards,

Z
Zoltan Palffy 👤 Member for 17 years

Using store period performance will put the actual cost into the correct time frames.

why is the contractor reluctant to do this ?

Z
Zoltan Palffy 👤 Member for 17 years

Using store period performance will put the actual cost into the correct time frames.

why is the contractor reluctant to do this ?

Featured Partner

Top Posters

Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
yerukalapudi
1 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts

Our Partners