Imported Material Resources Budget Units & Duration set to zero

1 reply [Last post]
Mohamed El Turky
User offline. Last seen 8 years 36 weeks ago. Offline
Joined: 8 May 2013
Posts: 5
Groups: None

Hi Everyone, 

i just imported a programme, i discovered that durations & budget units of material resources are set to zero, any advice ?

Best regards,

Replies

Alain De leon
User offline. Last seen 8 years 20 weeks ago. Offline
Joined: 15 Jun 2012
Posts: 18
Groups: None

check your resources if there is price / unit and quantity on the budgeted units