my senior ask to schedule mep of a project. he gave me the master schedule of that project. In that master schedule only Early Start and Early Finish time for MEP is given. As this is my first project and i had no previous experience in this, advice from your side is most precious.
So before starting what all things are required .
Member for
12 years 6 months
Member for12 years6 months
Submitted by paulrajanpullan on Fri, 2013-05-03 13:07
now i have an idea about the fix's and all. its all i got from your discussions. so thanks for that tooo. but my problem is how we set relation ship through these fix's
Send me a message with your email and I will send you a method statement for MEP planning that I wrote for the CIOB publication Guide to Good Practice of Time management in Complex Projects.
Member for
13 years 11 monthsHi Mike Testro,Would you like
Hi Mike Testro,
Would you like to help me to send method statement for MEP planning for the CIOB?
Thank You.
B/R Sagar Hassan
E-Mail : sagar_karachian_2002@yahoo.com
Member for
9 years 11 monthsHi, Can someone send
Hi,
Can someone send me productivity norms for calculation of manpower/Manhours for MEP Projects & Planning Method statement.
Regards,
Abdul Fattah
q_fattah@yahoo.com
Member for
19 years 10 monthsHi Paul The key to MEP
Hi Paul
The key to MEP planning is the interface between the structure and finishing tasks and the several stages of the MEP works.
If your programme is not sufficiently detailed then you will not be able to programme the MEP.
For instance in the ceiling void there are four interfaces with the suspended ceiling and the MEP installation.
Can you see on your programme when the roof zone / basement is ready to take the plant?
When is your power on date?
Do you have any MEP schematic drawings to see where the systems routes are?
Best regards
Mike Testro
Member for
12 years 6 monthshai friends my senior ask to
hai friends
my senior ask to schedule mep of a project. he gave me the master schedule of that project. In that master schedule only Early Start and Early Finish time for MEP is given. As this is my first project and i had no previous experience in this, advice from your side is most precious.
So before starting what all things are required .
Member for
12 years 6 monthsthanks mike.. now i have an
thanks mike..
now i have an idea about the fix's and all. its all i got from your discussions. so thanks for that tooo. but my problem is how we set relation ship through these fix's
Member for
19 years 10 monthsHi Paul Welcome to planning
Hi Paul
Welcome to planning planet.
Send me a message with your email and I will send you a method statement for MEP planning that I wrote for the CIOB publication Guide to Good Practice of Time management in Complex Projects.
It was never used.
Best regards
Mike Testro