Detailed mep planning procedure

Member for

9 years 11 months

Hi,

 

Can someone send me productivity norms for calculation of manpower/Manhours for MEP Projects & Planning Method statement.

 

Regards,

Abdul Fattah

q_fattah@yahoo.com

Member for

19 years 10 months

Hi Paul

The key to MEP planning is the interface between the structure and finishing tasks and the several stages of the MEP works.

If your programme is not sufficiently detailed then you will not be able to programme the MEP.

For instance in the ceiling void there are four interfaces with the suspended ceiling and the MEP installation.

Can you see on your programme when the roof zone / basement is ready to take the plant?

When is your power on date?

Do you have any MEP schematic drawings to see where the systems routes are?

Best regards

Mike Testro

Member for

12 years 6 months

hai friends

 

my senior ask to schedule mep of a project. he gave me the master schedule of that project. In that master schedule only Early Start and Early Finish time for MEP  is given. As this is my first project and i had no previous experience in this, advice from your side is most precious.

 

So before starting what all things are required . 

 

 

   

 

 

Member for

12 years 6 months

thanks mike..



now i have an idea about the fix's and all. its all i got from your discussions. so thanks for that tooo. but my problem is how we set relation ship through these fix's 

Member for

19 years 10 months

Hi Paul

Welcome to planning planet.

Send me a message with your email and I will send you a method statement for MEP planning that I wrote for the CIOB publication Guide to Good Practice of Time management in Complex Projects.

It was never used.

Best regards

Mike Testro