Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Base Line

2 replies [Last post]
Mohideen safi
User offline. Last seen 5 years 33 weeks ago. Offline
Joined: 10 Aug 2012
Posts: 3
Groups: None

hi anybody can answer

I updated my progress in P6 and i want this updated shedule as a new baseline. How can i change it in primavera P6?

 

Replies

Mohideen safi
User offline. Last seen 5 years 33 weeks ago. Offline
Joined: 10 Aug 2012
Posts: 3
Groups: None

thanks gary

Gary Whitehead
User offline. Last seen 5 years 25 weeks ago. Offline

Create a copy of your updated programme, and re-name it something like "Baseline -data date"

 

Then Open your original programme, go to Project > Maintain baselines > Add > Convert another project > select your new baseline

Once that is done, go to Project > Assign baselines > select your new baseline from the drop-down list under whichever baseline type you want to assign it to (Project, primary, secondary, or tertiary)