Problem with baseline incluing actual date

A
Amir Mina 👤 Member for 18 years 11 months

Dear All,

Plz help

I've a baseline schedule with some actual dates and duatation % complete. but when i assigned the same to updated prgramme the BL start and BL finsh dates are not the same i assigned ..............

Regards,

Amir

Forum Sponsor

Top Posters

bal aji
2 posts
Lee Mallek
23 posts
Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts