Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Planning the work of MEP,Floor, Ceiling and Wall activities in a building tower

4 replies [Last post]
Ismayil Mammadov
User offline. Last seen 12 years 1 day ago. Offline
Joined: 6 Apr 2012
Posts: 9
Groups: None

Dear Planners,

i am nearly to prepare comprehensive plan for the interior works and MEP(Mechanical,electrical,plumbing) for the Tower that we are building. structural works is ongoing and soon we will mobilize to start with the MEP work.

 

Currently i should plan the other activities and logics in exact order to control of MEP works and overlap them with others.

i have identified essential activities per floor which comprises everything:

removing props;

concrete repair works;

block works(masonry);

waterproofing;

MEP 1st fix;

MEP 2nd fix;

Walls plasted;

walls tiles;

painting;

raised floor;

floor tiles;

ceiling grids;

Fiber optic;

Doors and Windows;

install equipment(kitchen parts);

the question is that what is the best way to identify the logics between them?

 

Thank you in advance,

Ismayil

Replies

Ismayil Mammadov
User offline. Last seen 12 years 1 day ago. Offline
Joined: 6 Apr 2012
Posts: 9
Groups: None

Thank you very much Mike,

it is very detailed answer to me.

 

Regards,

Ismayil

Sunil Babu
User offline. Last seen 5 years 15 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Thanks Mike,

Your description is very much informative..

Regards

Sunil

Sunil Babu
User offline. Last seen 5 years 15 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Thanks Mike,

Your description is very much informative..

Regards

Sunil

Mike Testro
User offline. Last seen 36 weeks 19 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ismayil

MEP First Fix does not follow a floor by floor logic.

You have to look at the building as a whole unit and look at where the MEP elements start and stop within the structure.

Its like human anatomy. 

In respect of First fix MEP you have to look at the structure as an organic person and connect the organs to the nerves by a series of conduits - Air channels - Nerve systems - Waste Channels.

2nd Fix and finals can then be developed on a foor by floor basis  until they are all complete and final test and commissioning starts which then reverts back to the whole body concept. 

You have to remember the following basic elements.

1. MEP 1st Fix works connect one piece of kit ot another - these could each be at any location in the building.

1.1  So you have a number of  AHU's on the roof connecting to any number of A/C outlets at different levels in the builing.

1.2  So first determine a milestone when the structure is ready for each AHU to be installed and add a succesor task for that work 

1.2.1 Then fix a milestone when the 1st horisizontal distribution ductwork can be istalled and add a succesor task for that work .

1.2.2  Then fix a milestone when the vertical risers are ready for the vertical ductwork to be istalled and add a succesor task for that work

1.2.3 Then fix a milestone when the next horizontal milestone can be installed.

1.2.4  When all three milstone are in place then link them to another task called Connect Sytem Horizontal and vertical for each indiviual system

Note. I was on a project in Tolouse in France whe there were 47 air handing unite each sevine a different duct route - so there were 47 systems in my 1st fix MEP programme.

1.2.5  This last task is then linked to a milestone - AHU System ready for Wild Air.

1.3 This milestone is then linked to the last of the Finals task in the 2nd Fix operation which then is linked to Start Test and Commissioning.

Note - There are a lot of other cascades at Project Level leading to the same milestone. 

2. You have a Transfromer in the basement that reduces to the 11kv intake to a 120 / 240 v output

2.1 There will the be a series of distribution cable that connect to MCB's at each level and then on to DB's in each zone.

2.2 From each DB there will be a series of cables to each outlet - and that is where the Building Level work zone relates to the MEP 1st Fix task.

Final Note: There are many interfaces at 2nd fix work between MEP and other trades in both Floor Ceiling and Wall zones at each work zone - and again at floor level.

The only way that these can be integatrated properly and to retain a the true critical path is to use bottom up programming method.

Best regards

Mike Testro

Best regards

Mike Testro