You're right Mr. Daniel. Some of my total floats are negative already. I check out some links and construction procedures to be able to lessen all the negative floats. Thanks a lot.
Best regards,
Darwin
Member for
24 years 1 month
Member for24 years1 month
Submitted by Daniel Limson on Tue, 2011-06-14 06:33
You need to check further and investigate a little bit more. Late Dates are supposed to be the latest dates you can delay an activity without delaying some key dates and/or the overall completion date. In other words, previously you had floats on these activities, now you are saying that 'Late Dates' are earlier than the 'Early Dates', the only logical explanation to this anomalies is that you now have a negative float on some of these activities that is why you have this case. Check 'total float', if you have negative floats then late dates will be earlier than the early dates
Member for
19 years 10 monthsHi Darwin Negative float is
Hi Darwin
Negative float is usually caused by a Must End On constraint.
Best regards
Mike Testro
Member for
14 years 5 monthsYou're right Mr. Daniel. Some
You're right Mr. Daniel. Some of my total floats are negative already. I check out some links and construction procedures to be able to lessen all the negative floats. Thanks a lot.
Best regards,
Darwin
Member for
24 years 1 monthDarwin, You need to check
Darwin,
You need to check further and investigate a little bit more. Late Dates are supposed to be the latest dates you can delay an activity without delaying some key dates and/or the overall completion date. In other words, previously you had floats on these activities, now you are saying that 'Late Dates' are earlier than the 'Early Dates', the only logical explanation to this anomalies is that you now have a negative float on some of these activities that is why you have this case. Check 'total float', if you have negative floats then late dates will be earlier than the early dates
Best regards,
Daniel