Early and Late Dates

Hi All,

Recently I've created 3rd revised baseline programme for our company.  But when I assign our new baseline programme, I've noticed that some of the lates dates are earlier than the early dates.  Is it really possible to happen?

Thanks & Regards,

Darwin

M
Mike Testro 👤 Member for 20 years 7 months

Hi Darwin

Negative float is usually caused by a Must End On constraint.

Best regards

Mike Testro

D
Darwin Graciano 👤 Member for 15 years 1 month

You're right Mr. Daniel. Some of my total floats are negative already. I check out some links and construction procedures to be able to lessen all the negative floats. Thanks a lot.

Best regards,

Darwin

D
Daniel Limson 👤 Member for 24 years 9 months

Darwin,

You need to check further and investigate a little bit more. Late Dates are supposed to be the latest dates you can delay an activity without delaying some key dates and/or the overall completion date. In other words, previously you had floats on these activities, now you are saying that 'Late Dates' are earlier than the 'Early Dates', the only logical explanation to this anomalies is that you now have a negative float on some of these activities that is why you have this case. Check 'total float', if you have negative floats then late dates will be earlier than the early dates

Best regards,

Daniel

Featured Partner

Top Posters

Alex Lyaschenko
26 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts
Jerry Robinson
2 posts
James Williams
75 posts
Elyar Safarov
1 posts

Our Partners