Hi Stormy



When I was aked at an interview what shipbuilding experience I had I said "It is just like a long steel building that floats"



I did not get the job but the principle applies as with a building start at the bottom and work up.



So lay the keel - get the frame in place - fit in the kit between decks - fix the external plating - fit out the interior - order the champagne for the launch.



As I have said many times - if you can’t build it you can’t plan it.



Good luck anyway.



Best regards



Mike Testro.