Darren, It has been a while since this posting was made but an outline of ADePT (methodology and software) has been uploaded on the WIKI - under 'planning software'. This will answer some of your questions.
In essence, however, the iterations that are identified through modelling the integrated process in the ADePT Design Builder application are not influenced by time (otherwise the iterations could not be analysed as they have embedded backward flowing logic) - they are simply information dependencies and interdependencies between activities. To enable two-way synchronisation with existing planning tools (CPM-based) a 'filter' has been developed that captures backward flowing logic at the interface between the tools and converts the data to enable scheduling using CPM (iterations included but represented as periods of parallel working).
This data, in combination with the backward flowing logic (which is retained in the ADePT software) enables 'lean' principles to be applied - basically, production control principles adapted to take account of the fact that an iterative loop is never 'made ready' in true production control terms. The ongoing use of the ADePT Design Manager application (sister product to the ADePT Design Builder) enables development of further detail as the process progresses, gaining commitments from those responsible, and identifying / removing constraints ahead of them creating delay is founded in lean and is a pre-cursor for agile. As such, there are great parallels between ADePT and Agile.
Futher on information on ADePT and Design Management can be found, videos of the application in use, and a downloadable trial version of the software can be found at: www.adeptmanagement.com
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Darren, It has been a while since this posting was made but an outline of ADePT (methodology and software) has been uploaded on the WIKI - under 'planning software'. This will answer some of your questions.
In essence, however, the iterations that are identified through modelling the integrated process in the ADePT Design Builder application are not influenced by time (otherwise the iterations could not be analysed as they have embedded backward flowing logic) - they are simply information dependencies and interdependencies between activities. To enable two-way synchronisation with existing planning tools (CPM-based) a 'filter' has been developed that captures backward flowing logic at the interface between the tools and converts the data to enable scheduling using CPM (iterations included but represented as periods of parallel working).
This data, in combination with the backward flowing logic (which is retained in the ADePT software) enables 'lean' principles to be applied - basically, production control principles adapted to take account of the fact that an iterative loop is never 'made ready' in true production control terms. The ongoing use of the ADePT Design Manager application (sister product to the ADePT Design Builder) enables development of further detail as the process progresses, gaining commitments from those responsible, and identifying / removing constraints ahead of them creating delay is founded in lean and is a pre-cursor for agile. As such, there are great parallels between ADePT and Agile.
Futher on information on ADePT and Design Management can be found, videos of the application in use, and a downloadable trial version of the software can be found at: www.adeptmanagement.com