Yes the block wall has a pred of the permit. But the permit doesnt have a pred. That is what is putting it at the data date. I have tried all the options in the task field and have not gotten any different results.
It will have a predecessor! The start of the wall is a predecessor of the finish of the getting the permit. With -30 days lag (lead).
If its date isnt moving as the walls dates move, something is wrong. Try making the block wall "reminder" a milestone, with duration of zero, and then have the activity to apply for the permit as a FS successor of that milestone.
If it doesnt work then, something else is going on.
What I am trying to do is set a reminder to get my block wall permit 30 days before I start the wall. So I did as you say and did a SF and even tried a SS with -30 lag and it still just sits at the data date since it has no pred. I dont want to put a pred. on it so that it will float with the wall. If I can start early or late, I still want to remember to get it 30 days before I start the wall.
I am by no means an expert on any software package (with apologies to Vladimir, none of them do all of what I want them to do, although Spider may come closest!).
However I would think that using the following logic relationship should do the trick:
A = Install Window
B = Order Window
Pred A start-to-finish -20 Succ B
A -> SF-20 -> B
One word of warning: if using MS Project, be aware that the late dates it computes for the successor in SF relationships are not intuitively obvious (IMO, they are one unit too great). In the above example, if A has an early (or late) start date of Day 50, it will give B a finish date of Day 30, when the finish of Day 29 is what IMO would be consistent with the usual approach of having activities always finish at the end of a time unit.
I dont know about Primavera, Spider, Open Plan, etc.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thanks!!!!!!!!
That works perfect
Thank you Thank you Thank you Thank you
Ben,
On the reminder activity, tick the zero free float in the constraints dialog box.
Regards,
Larry
Yes the block wall has a pred of the permit. But the permit doesnt have a pred. That is what is putting it at the data date. I have tried all the options in the task field and have not gotten any different results.
It is driving me crazy.
Ad Ben,
It will have a predecessor! The start of the wall is a predecessor of the finish of the getting the permit. With -30 days lag (lead).
If its date isnt moving as the walls dates move, something is wrong. Try making the block wall "reminder" a milestone, with duration of zero, and then have the activity to apply for the permit as a FS successor of that milestone.
If it doesnt work then, something else is going on.
Thanks for the reply.
I did try that.
What I am trying to do is set a reminder to get my block wall permit 30 days before I start the wall. So I did as you say and did a SF and even tried a SS with -30 lag and it still just sits at the data date since it has no pred. I dont want to put a pred. on it so that it will float with the wall. If I can start early or late, I still want to remember to get it 30 days before I start the wall.
Anyone????
Hi, Ad Ben.
I am by no means an expert on any software package (with apologies to Vladimir, none of them do all of what I want them to do, although Spider may come closest!).
However I would think that using the following logic relationship should do the trick:
A = Install Window
B = Order Window
Pred A start-to-finish -20 Succ B
A -> SF-20 -> B
One word of warning: if using MS Project, be aware that the late dates it computes for the successor in SF relationships are not intuitively obvious (IMO, they are one unit too great). In the above example, if A has an early (or late) start date of Day 50, it will give B a finish date of Day 30, when the finish of Day 29 is what IMO would be consistent with the usual approach of having activities always finish at the end of a time unit.
I dont know about Primavera, Spider, Open Plan, etc.