Yes, you are right, Its a vessel in a desalination plant. I mean the installation of this vessel (and everything associated with it, including the pump). Thanks.
I need for example in full details about using Primavera p3 for any propject such as WATER working in pump water , i need infact, the after am compelting my tendor , how can using activites , duration acost , resoures etc
If have any perpre example dont hestaite to send on my mail: E-mail: yousifalaubidi@yahoo.
I need for example in full details about using Primavera p3 for any propject such as WATER working in pump water , i need infact, the after am compelting my tendor , how can using activites , duration acost , resoures etc
If have any perpre example dont hestaite to send on my mail: E-mail: yousifalaubidi@yahoo.
Just to clear the confusion. I think this is a pressure vessel or a distillation unit in a desalination plant, correct me if I am wrong. Do you mean the pumps associated with these?
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Dear Ted Davies
can you send me the total step of alaysisi the pump instalition by using PRIMAVERA P3 , WITH THANKS
Yes, you are right, Its a vessel in a desalination plant. I mean the installation of this vessel (and everything associated with it, including the pump). Thanks.
Dear Adil Gibreel
I need for example in full details about using Primavera p3 for any propject such as WATER working in pump water , i need infact, the after am compelting my tendor , how can using activites , duration acost , resoures etc
If have any perpre example dont hestaite to send on my mail: E-mail: yousifalaubidi@yahoo.
com
With Regreds
Engineer Yousif ALaubidi
Iraq
Basra
21/11/2005
Dear Adil Gibreel
I need for example in full details about using Primavera p3 for any propject such as WATER working in pump water , i need infact, the after am compelting my tendor , how can using activites , duration acost , resoures etc
If have any perpre example dont hestaite to send on my mail: E-mail: yousifalaubidi@yahoo.
com
With Regreds
Engineer Yousif ALaubidi
Iraq
Basra
21/11/2005
Just to clear the confusion. I think this is a pressure vessel or a distillation unit in a desalination plant, correct me if I am wrong. Do you mean the pumps associated with these?
Dear Ted Davies
I need too the step of instelling by using Primavera p3 in my work .......
With regreds
Engineer
Yousif
Iraq-Basra