copying activities in P v8.1

1 reply [Last post]
abdallah riad
User offline. Last seen 11 years 24 weeks ago. Offline
Joined: 20 Feb 2004
Posts: 23
Groups: None

Hi all,

is it possible to activities from one project to another.

i tried that but it did not work.

 

regards,

 

abdallah

Replies

Christopher Hall
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 17 May 2012
Posts: 42
Groups: None

Abdallah,

Open both projects at once, then copy/ paste activities.  Navigate from the activity window.

Chris