Overall % Complete

Hi All,

Would like to know if we can show overlla % compelete in PRimavera updated schedule.

I have been progress measuring using excel in which some activities progress is measured by

  • Manhours
  • Cost

But the OVerall weightage is claulated based on the assigned weighate as per Contract for example

Engineering - 15%

Procurement - 40%

Construction - 35%

Commissioning - 10%

 

So can we show this in PRimavera 6 updated schedule ?

Regards

Jithin

R
Rodel Marasigan 👤 Member for 19 years 8 months

You can create a resources for that purpose and assign cost to all activities, factored by Weighting that you have per EPCC WBS

D
david kelly 👤 Member for 10 years 5 months

You could use the WBS facility 'WBS Milestone % complete' in order to exactly track the EPCC percentages you quote.

Featured Partner

Top Posters

Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts

Our Partners