Export of Baseline

6 replies [Last post]
Jithin Kambhikanam
User offline. Last seen 1 year 3 weeks ago. Offline

Hello Everyone,

 

I am using  P6.18.8.0 version.

When I export it in XER format, the baseline is not been exported.

when I export in XML format again the baseline is not exported.

Any solution to this.

Thanks

Jithin 

 

Replies

Jithin Kambhikanam
User offline. Last seen 1 year 3 weeks ago. Offline

Hi Alex,

 

Ya its working. I exported a XML File and the baseline was in it.

Thanks for the tip.

 

Regards

Jithin

Santosh Bhat
User offline. Last seen 13 weeks 3 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Alexandre,

Yes you are corect. Sorry, its been a long time since I've had to use the XML format.

Jithin Kambhikanam
User offline. Last seen 1 year 3 weeks ago. Offline

Hi Alex,

 

I did export in XML Format, but again its not exporting the baseline.

 

And while exporting its asking if to include baseline and I have selected the baseline to be exported. But after exporting the and importing it to another machine I am not able to see the exported Baseline.

 

Is it a settings issue of Exporting Machine or Importing Machine ?

 

Thanks 

Jithin

Santosh Bhat
User offline. Last seen 13 weeks 3 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Baselines are not exported to those formats, you need to go MAINTAIN BASELINES>RESTORE BASELINES then export this restored project seperately. Remembe to then re-attach the baseline to the original project.