Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

BL1 not showing correct dates - sorted Now

1 reply [Last post]
Thomas Nicholson
User offline. Last seen 3 weeks 1 day ago. Offline
Joined: 4 Oct 2006
Posts: 87
Groups: None

Morning all, 

I've recently had installed a newer (17.3) version of P6.  I've got a copy of a submission from last month which I'm comparing to a submission this week.  However for some reason the dates aren't coming through correctly.

I've assigned the old one as BL1 and as there is no change in a LOE activity date I'd expect it to show the same but for some reason it's showing a date a year out.   Other dates are out too and I cannot understand why it's not all as some are fine.

Any advice folks?

Thanks

 

EDIT - it was the earned value setting.

Replies

Zoltan Palffy
User offline. Last seen 20 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

that will do it