Good afternoon/Morning depending where you are.
A fellow planner has come to me with an issue today, he's finding odd calculations in his plan. I've opened the same plan (we're in the same server).
On mine the original duration is different, the remaining is different to the same activity in the same plan when opened on his machine.
We've been through the usual checks to see if his calendars are different etc but nothing seems to be different in any options so we can't understand why his appears to be working on a different calendar to mine.
Example.
Car park opens (on mine) remaining 36d opens 22-12-19
Car park opens (on his) remaining 7d opens 22-12-19
Both have 7 day working calendars with no resources set up on either. It's the same plan opened on 2 seperate machines.
Does anyone have any other checks, or even ideas as to what is causing this?
Thanks in advance,
Thom
Replies