Remaining Duration - Update Automatically?

E
Emma Lang 👤 Member for 9 years 11 months

Is there a setting so the Remaining duration updates automatically for activities which are in progress. 

I.e. for a 10 day duration with an actual duration of 5 days then the remaining would be calculated to 5 days?

I currently have a 64 day activity, when I schedule it a a few weeks later than the start the remaining duration is still 64 days. It is set to Physical % Complete, at 95% complete. 

I've tried to change lots of different settings in the project window, user preferences, schedule options etc. 

Any help would be appreciated. 

Z
Zoltan Palffy 👤 Member for 17 years

what you can is to run a global change to make the duration % complete equal to the physcial % complete

go to tool global change 

New

where Percent Complete Type equals Physical 

then duration % complete = Physical % complete

now on the rigth select Change

then on the botton right select Commit Changes

Featured Partner

Top Posters

Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts
Patricio_aoa
0 posts
James Williams
75 posts
Philip Assou-Dodji
1 posts
jeoffrey reyes
15 posts
markg
0 posts