Instead please take a look at the folllowing link. There you will see a sample page showing crew composition and daily output.
Be reminded that crew production rate is a function of the crew composition. Changing a single component usually will result in a change in production rate. Usually the change is not linear to a change in manpower even if only manpower resources are used, more so if production equipment are a component of your crew.
Consider using RS Means as a reference in the absence of company records. It is critical you understand that the components work as as a group. Increasing or decreasing individual team members within the crew most probably will invalidate average crewhours per unit of work, these numbers are valid for the specific crew composition, nothing more, nothing less.
Activities in building construction are certain. Volume of works can be calculated exactly. So manpower always depend on the volume of works and maneuverability. However, technology becomes sophisticated that sometimes reduces the number of manpower as compared from traditional or conventional ways.
Member for
7 yearsReceived Ali Brother.Thanks
Received Ali Brother.
Thanks Alot
God Bless U
Member for
7 years 7 monthssent
sent
Member for
7 yearsRafaelThanks and got it.
Rafael
Thanks and got it.
Member for
7 yearsDear Mohammad Ali,Thanks for
Dear Mohammad Ali,
Thanks for the response. I really appreciate if you send me some files.
Here is my email address
(Saqib.bhatti92@gmail.com )
Member for
21 years 7 monthsThe link is no longer
The link is no longer available.
Instead please take a look at the folllowing link. There you will see a sample page showing crew composition and daily output.
Be reminded that crew production rate is a function of the crew composition. Changing a single component usually will result in a change in production rate. Usually the change is not linear to a change in manpower even if only manpower resources are used, more so if production equipment are a component of your crew.
RS Means - How to use the Unit Price pages
Member for
7 years 7 monthsWhat is your Email and I will
What is your Email and I will send you some files?
Member for
7 yearsDear Rafael, Thanks for your
Dear Rafael,
Thanks for your reply
but link is not opening. I think there is some kind of an error .
Member for
21 years 7 monthsConsider using RS Means as a
Consider using RS Means as a reference in the absence of company records. It is critical you understand that the components work as as a group. Increasing or decreasing individual team members within the crew most probably will invalidate average crewhours per unit of work, these numbers are valid for the specific crew composition, nothing more, nothing less.
Click to Download - RS Means PowerPoint Presentation
Good Luck.
Member for
7 yearsYes you are right but i have
Yes you are right but i have to start form somewhere.
Atleast there are some standards which we used at the start of the project. I really don't have the site experience
Member for
7 yearsThanks but i didn't find
Thanks but i didn't find anything .
Member for
16 years 3 monthslook on this site under the
look on this site under the tab up top labeld Build Times
Member for
19 years 1 monthActivities in building
Activities in building construction are certain. Volume of works can be calculated exactly. So manpower always depend on the volume of works and maneuverability. However, technology becomes sophisticated that sometimes reduces the number of manpower as compared from traditional or conventional ways.