An application events has been intercepted. Please note the reference code for reference. Event code F429B079

3 replies [Last post]
Viet Tran
User offline. Last seen 1 year 25 weeks ago. Offline
Joined: 28 Feb 2017
Posts: 13

Hi everyone,

When I update my baseline in Primavera P6, an error occurs as follow "An application events has been intercepted. Please note the reference code for reference. Event code F429B079". So, I can not use update BL function in P6 anymore.

Could you help/instruct me how to solve this problem.

Thanks so much,

Viet Tran,

Replies

Zoltan Palffy
User offline. Last seen 16 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

glad I could help 

Viet Tran
User offline. Last seen 1 year 25 weeks ago. Offline
Joined: 28 Feb 2017
Posts: 13

Dear Zoltan Palffy,

Thanks for your consulting. It's now running ok after I re-installed the correct Java version integrated P6.

Thanks and regards,

Viet Tran,

Zoltan Palffy
User offline. Last seen 16 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

you have the incorrect java version 

to resolve this issue, please follow these instructions:

  1. Uninstall the incorrect Java version from the machine it is currentyl conflicing wih p6
  2. Install a Java version that appears in the Tested Configuration list for your P6 version. 
  3. Configure the JAVA_HOME environment variable to point to this new java version in the System Environment variables for P6