Schedule% complete & Performance % complete is not appearing

A
adab azeez 👤 Member for 9 years 11 months

Greetings to all.
I am updating a project in primavera.I need to present schedule % and performance % in the WBS of activities. But it is always showing zero, though the activity sch.% and performance% are rolling up with the update.
Need a guidance.

Thanks in advance.

A
adab azeez 👤 Member for 9 years 11 months

Thank you Mr. Zoltan.
If resource unit per price is not zero then % progress will roll up with every status update. I have done it.

Z
Zoltan Palffy 👤 Member for 17 years

create an activity for that particular wbs and give it the activity TYPE of wbs summary then it will roll up and summarize that particular wbs for you. You can not roll up the wbs in the way that you are doing it becasue activities can use different wats to mecasure their progress you can use duration % complete, physical % complete or units % complete. So if you tried to summarize them by youe would be mixing applles and oranges and bananas. The soultion is to use WBS summary.

Featured Partner

Top Posters

MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts