Exporting from P6 16.1 to MSP 2010

E
Emma Lang 👤 Member for 9 years 11 months

Hello, 

What is the easiest and quickest way of exporting from P6 to MSP without dates and hours looking mental? I've tried doing a straightforward export but a lot of my dates have changed, even for completed activites, and the work is also incorrect?

Any help would be appreciated. 

Thanks

D
David Kelly 👤 Member for 21 years 9 months

The only safe way to do it is to use Collabro's Legare software. 

E
Emma Lang 👤 Member for 9 years 11 months

ah.. thanks. Tried that yesterday, dates were all over the place. 

Looks like I'll need to check the dates of 2000 activities line by line

Thanks anyway

 

Z
Zoltan Palffy 👤 Member for 17 years

try the html method

does not matter what you do they will never match the way msp handlesa wbsis different,  calendars are different, the alogrithm calculation for the forward and backward pass is different, the way MSp handles milestone is different. Just be glad that you do noy have to type the activities again

Featured Partner

Top Posters

PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts