Removal of Constraint Issue

1 reply [Last post]
Ijaz Ahmad
User offline. Last seen 7 years 39 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 42
Groups: None

Hello Guys,

I am using Primavera version 8.2. I am having issue with the constraint date removal. When I remove some contraint on a finish date and set it to none, I still see a star beside the finish date and the late finish date still show the constraint date which I previously set while applying the constraint. Did any body notice this problem? Any solution will be highly appreciated.

Thanks

Ijaz

Replies

Zoltan Palffy
User offline. Last seen 29 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

1. did you recalcualte the schedule ?

2. is this activity linked to another activity in a DIFFERENT project. If so the * will stil be there