why there is deviation in original duration if "Hide if empty" is unchecked ?

A
adab azeez 👤 Member for 9 years 11 months

Greetings to All.

I am making a schedule on P6 in which my project original duration appears to be very less. But whenever i check "hide if empty" in group and sort tab, It shows the project's correct original duration. Is there something wrong with my schedule ?

if its an error then how to fix it?

Thanks in advance 

D
David Kelly 👤 Member for 21 years 8 months

This relates to the way durations are calcuated in summary bars, in particular which calendar to use to "back-calculate" the durations from the dates in the summary (which is how those durations are calculated)

If all of the activities within a single Group-and-Sort band share the same calendar, that calendar will be used to calculate the summary bar durations, other wise the so-called "Default" calendar will be used. 

By using "hide if empty" the number of Group-and-Sort bands will vary, and therefore the summary-duration rules will change.

The above is true from version 6.7 onwards. 

Featured Partner

Top Posters

Robert Guers
1 posts
Jerry Robinson
2 posts
James Williams
75 posts
Elyar Safarov
1 posts
Christopher Ganotice
1 posts
Ola Gbotoso
0 posts
pennyu
0 posts
jaasland
0 posts
Doron El
3 posts
Erim INANC
2 posts

Our Partners