Issue with Role Limit in Resource Useage Profile

I am having an issue with the Role "Limit" displaying correctly in my Resource Useage Profile. I have a Role, titled D7E, and we have (2) of these dozers in the company. So, I assigned 2 Units/ Day as the Max Units per Time for the D7E Role. However, when I look at the limit line for that Role in the Resource Profile, it indicates a limit of 1 Unit/ Day. This causes the D7E to show an overallocation of 1, even though this is incorrect. Am I missing something?