Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Remainig Unit/Time

2 replies [Last post]
moutaz aldeib
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Hi Planners

I am updating a project schedule with resources and after updating I found that the remaining units/time for completed activity is still fixed 8h/d. Is this right? even though the remaining units for that activity is zero.

Best,

Moutaz

Replies

moutaz aldeib
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Thanks Zoltan for your confirmation

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

yes that is corect that does not change