Help Please - Network Diagram

Hello. I'm in need for some help. The spec (shown below) is calling for a Network Diagram. I have used the Activity Network view to create one and have tinkered in Visualizer. A big problem for me is that the project goes from 2012 into 2016 which is making me have sheets upon sheets of printed material, even on large sized plots.

The first one I sent over had 27 11x17 sheets and the Contracting Officer went ape xxxx. Originally there were 80, but I deleted the empty sheets. He wants plots. So I sent him six 40x30 sheets, but the Critical Path wasn't shown (printed in b&w, trying to save money). Any ideas would be greatly appreciated (I already thought of using a highlighter on the critical activities, but don't think tha'd go over well).

SPEC:

3.5.5. Network Diagram

The network diagram is required for the Preliminary, Initial, and Periodic

Updates. The network diagram shall depict and display the order and

interdependence of activities and the sequence in which the work is to be

accomplished. The Contracting Officer’s review of the Contractor’s

compliance with the conditions outlined in this paragraph will include,

but is not limited to, the following:

3.5.5.1. Continuous Flow

Diagrams shall show a continuous flow from left to right, with no arrows

from right to left. The activity number, description, duration, and

estimated earned value are to be shown on the diagram.


3.5.5.2. Project Milestone Dates

The diagram must include the project start date, any contract required

interim completion dates, and contract completion dates.

3.5.5.3. Critical Path

The critical path must be clearly shown. (Color Prints I suppose)

3.5.5.4. Banding

Activities are to be organized as directed to assist in the understanding

of the activity sequence.

Typically, this flow will group activities by category of work, work area,

and/or responsibility.

Thanks,

Andre

R
Raymund de Laza 👤 Member for 16 years 7 months

Andre,

Customize the Bars by using a Pattern on it so that even printing in B/W the Critcal Activities will be recognized.

 

Regards,

C
C. Andre McMillan 👤 Member for 13 years 3 months

Raymund - totally agree, but the Contracting Officer does not. When he said he couldn't see the Critical Path, I told him to look at the Critical Path gantt chart that was also provided. Not good enough for him. He sees black & white with as much common sense as a shelled walnut.

Zoltan - thank you for those ideas. If he keeps belly aching, I may try that multiple plot approach.

Johannes - I;m sure those looked pretty good, especially if you could get them on a max of 3 sheets. I'm at 8 now for legibility and it's beyond waste.

 

Thanks - Andre

J
Johannes Vandenberg 👤 Member for 16 years 5 months

Hi Andre

I agree with Raymond. I still see the requirements in the administration procedures for off-shore contracts. My experience is that the scheduling model shall be created as an Network diagram but the the Schedule instances are presented in an Gantt barchart.

However nicely plotted diagrams look impressive! Takes me back to the late seventies . We drafted them by hand!

Regards Johannes

Z
Zoltan Palffy 👤 Member for 17 years

I could see this being 5 seperate plots but not one

if you want to get this try this

3.5.5 Network Diagram - Plot this using a plotter click on the activity network icon

3.5.5.1. Continuous Flow - I do not think that you can trun off the arrows. You can modify the box to get the required data in the box. The activity number, description, duration, and estimated earned value.

3.5.5.2. Project Milestone Dates - The only way to get the project start date is to add it as a header or footer. Any contract required interim completion dates, and contract completion dates can be shown in the modified box but it will be for all activities not just milestones

3.5.5.3. Critical Path - yes color plot in red



3.5.5.4. Banding - you can use Grouping here but then this defeats the critical path item above

if seperate plots this makes more sense

3.5.5 Network Diagram - Plot this using a plotter click on the activity network icon

3.5.5.1. Continuous Flow - Plot a times scaled logic diagram from left to right and turn off the relationships This wil be on the rigth in the graph portion.  You can add columsn in the data table portion on the left to get the required data such as the activity number, description, duration, and estimated earned value.

3.5.5.2. Project Milestone Dates - Filter for milestones only. 

3.5.5.3. Critical Path - Filer of the critical ptha only and plot in the color redred

3.5.5.4. Banding - you can use Grouping here and group it any way that you wish

R
Raymund de Laza 👤 Member for 16 years 7 months

Andre,

I think that the Text of the Specs is considered obsolete, I have seen the same specs 20 years ago with one of the Projects I was assigned.

The layouts available from the Scheduling software or Customized layout according to Client's rep requirement will be acceptable.

 

Regards,

Featured Partner

Top Posters

Zainab El-Beialy
3 posts
Kamlesh Parmessur
4 posts
MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts