What are Out-of-sequence Activities?

What exactly is an out-of-sequence activity and why do I care? Learn more http://ow.ly/zx2NU

M
Mike Testro 👤 Member for 20 years 7 months

Hi Anand

A simpler more general definition is that Out of Sequence Working is when tasks on a programme are being executed in a different logical sequence to that intended as planned.

This happens on most projects and it should not be ignored but the logic changed to reflect what is actually happening.

Best regards

Mike Testro

A
Anand Kurmi 👤 Member for 15 years 2 months

Hi Emily,

When a successor activity starts earlier than predecessor, out of sequence occurs.

This affects the schedule when progressing update is based on retaine logic.

Featured Partner

Top Posters

Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts