Project changes tasks start time

Hello!

I'm trying to create project by importing data from xml-file. Almost everything is working fine, I get required resources and tasks? but when I click on task information - ok , all my tasks start dates are changed.

I guess, the question is not pretty clear, so I made a video for better understanding https://youtu.be/ey_3VHj5lck

T
Tom Boyle 👤 Member for 19 years 7 months

Aliaksei,

There is no logic (predecessors and successors) in the xml file.

The schedule re-calculates automatically after you open and close the Task Information dialog.  Without logic to push them out, all of the tasks are pulled back to the project start date.

You need to either a) include logic in the xml file; or b) include start-no-earlier-than constraints in the xml file; or c) ensure that task mode = "manually schedule" for all your tasks before it gets scheduled.  Only the first option is acceptable as a legitimate project scheduling practice.

Good luck, tom

Featured Partner

Top Posters

Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts
Jerry Robinson
2 posts
Elyar Safarov
1 posts

Our Partners