Summary duration % Complete

A
Ahmed KHR 👤 Member for 15 years 8 months

Dear Planners;

I'm worried about the Duration % complete on summary tasks on MS Project programme calculation!

 

So, Any body have an Idea about please share it.

 

Regards.

 

A
ali deveboynu 👤 Member for 16 years 3 months

% complete on summary task are calculated by simple aritmetic average , assume you have 2 task under summary task , which has 10 and 20 days durations and %40 and %50 completes , % complete calculates such as (40*10)+(50*20)/30

best regards

Featured Partner

Top Posters

Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts

Our Partners