Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Summary duration % Complete

2 replies [Last post]
Ahmed KHR
User offline. Last seen 6 years 36 weeks ago. Offline
Joined: 10 Nov 2010
Posts: 65

Dear Planners;

I'm worried about the Duration % complete on summary tasks on MS Project programme calculation!

 

So, Any body have an Idea about please share it.

 

Regards.

 

Replies

Ahmed KHR
User offline. Last seen 6 years 36 weeks ago. Offline
Joined: 10 Nov 2010
Posts: 65

Thank you Ali for the confirmation.

ali deveboynu
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 24 Mar 2010
Posts: 5

% complete on summary task are calculated by simple aritmetic average , assume you have 2 task under summary task , which has 10 and 20 days durations and %40 and %50 completes , % complete calculates such as (40*10)+(50*20)/30

best regards