Hi everyone
I have the follow problem.
I tried to built my project in MS Project 2007 but the duration of the task are very weird...ok...i have the calendar of this way...Monday to Sunday...From 7:00 am to 11:30am and From 1:30 pm to 7:00 pm.
The Begin date is the 5 of May of 2010 and the finish date is the 30 of May of 2010...well...Project say me that the duration is 43.41 days...hey hello, I tried to put any calendar 24 hours or the calendar that i customize but nothing work like a want...I want to show 25 days of duration...Can someone help me and show me what is the problem?...the MPP file is this and you can download from mediafire...the first group don’t have or be finished...but the second (Mechanical Activities) are like I want.
Thanks