Import form MSP 2007 to Primavera 6.1

S
Shahzad Sikandar 👤 Member for 20 years 5 months

Cherie



doesnt metter, even you save it in version 2003 (MSP), IT Atually uses the software system currently installed on your machine (in this case its MSP 2007).



you have to have MSP 2000, 2002/3 in order to import a MS project files into Primavera 5 or 6



but i am still looking for solutions.

cheers

C
Cherie S Blare 👤 Member for 20 years 6 months

Why not save in MSP 2003 ( as you can in MSP 2007 ) and then import / open up in P6 ? I think this can only be done in standalone P6 - not intranet licence based.



Regards



Cherie

P
Paul Harris 👤 Member for 25 years 3 months

The installation of MSP 2007 disables the import feature of P6.



Unloading MSP 2007 may resolve your problem.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

Featured Partner

Top Posters

Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts
Patricio_aoa
0 posts
James Williams
75 posts
Philip Assou-Dodji
1 posts
jeoffrey reyes
15 posts