Tracking The Quantities Using MSP2003

1 reply [Last post]
Md Dasuki Samad
User offline. Last seen 11 years 26 weeks ago. Offline
Joined: 4 Nov 2007
Posts: 8
Groups: GPC Malaysia
Hi,

Currently, I monitoring and scheduling highway & bridges project.
I’ve difficulties to track and find out the quantity of materials supposed to be ready at any date referred such as steel bars tonnage, m3 concrete and m3 of earthworks.
Those information are required in order for me to prepare the ’order material list’ for my project.
kindly please explain and advise me on how should i solve this matter.I also have no idea whether MSP2003 able to do this or not.
Please help.
Thank you.

Replies

Johny Kesserwany
User offline. Last seen 7 years 25 weeks ago. Offline
Joined: 18 Sep 2007
Posts: 118
Hi,

Did you assigned those quantities on related activities as resources?

If yes you can execute a report showing the workload by time period which will be your budgeted quantities/period.