Linking Tasks from 2 different projects

4 replies [Last post]
Tony Hughes
User offline. Last seen 17 weeks 19 hours ago. Offline
Joined: 22 May 2003
Posts: 64
Trying to link tasks from Design programme into Master Programme. The links are being created but the task is copied over to master programme thus creating two bars the same, any ideas on how to stop this doubling up happening

Replies

Tahir Naseem PMP,...
User offline. Last seen 5 years 39 weeks ago. Offline
Joined: 26 Oct 2006
Posts: 85
Dear
Thanks for the information
Regards
Tahir
Tony Hughes
User offline. Last seen 17 weeks 19 hours ago. Offline
Joined: 22 May 2003
Posts: 64
Cheers Will,

I eventually got it sorted by unticking the "shown external" boxes

Will Russell
User offline. Last seen 11 years 29 weeks ago. Offline
Joined: 9 Apr 2003
Posts: 48
Groups: None
Tony,
Project creates a ghost task when linking between projects is this what you are seeing? If it is go to Tools/Options/ on the view tab you will see that there are tick boxes for "Show external predecessors" and "Show external successors" unticking these might be the answer to your problem. Let us know if it is.
Will