As far as I know, the only way to allocate resources not proportinaly is to use the Task usage view: you can enter the exact amount of work you want in every cell, that is every day or week according to the Timescale zoom.
In no way will MS Project easily split the resource allocation to take advantage of every hole in the resource agenda; it is possible to set up the resource leveling to split the remaining work and therefore split a long task to make space for short allocations (ie a 1/2 day meeting in the middle of a 2 week task), but it is much less clever than the corresponding feature in P3.
Hi, firstly thanks for your interest. Ill try to explain with an example. Assume that an activity which has 5 days duration and also has 5 days slack. It has just 2 workers daily working as a resource it means 16 hours a day totally 80 hours for whole activity. If I want I can decrease the resources to 1 worker a day so the duration will increase to 10 days, finally its acceptable for my project because it doesnt change my critical path or it doesnt effect my cost the adjustment is done in available slacks.
I can do these without software and I couldnt reach the same optimizations with MS project. MSP divide resources equally to activity duration and it just make splits if its necessary but it cant increase the activity duration by allocating resources randomly although it has available slacks.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
thanks for your help Ill try these in p3 too.
Ersin
As far as I know, the only way to allocate resources not proportinaly is to use the Task usage view: you can enter the exact amount of work you want in every cell, that is every day or week according to the Timescale zoom.
In no way will MS Project easily split the resource allocation to take advantage of every hole in the resource agenda; it is possible to set up the resource leveling to split the remaining work and therefore split a long task to make space for short allocations (ie a 1/2 day meeting in the middle of a 2 week task), but it is much less clever than the corresponding feature in P3.
Regards
Hi, firstly thanks for your interest. Ill try to explain with an example. Assume that an activity which has 5 days duration and also has 5 days slack. It has just 2 workers daily working as a resource it means 16 hours a day totally 80 hours for whole activity. If I want I can decrease the resources to 1 worker a day so the duration will increase to 10 days, finally its acceptable for my project because it doesnt change my critical path or it doesnt effect my cost the adjustment is done in available slacks.
I can do these without software and I couldnt reach the same optimizations with MS project. MSP divide resources equally to activity duration and it just make splits if its necessary but it cant increase the activity duration by allocating resources randomly although it has available slacks.
My e-mail is: [email protected] I can send you the sample projects
hello,
can you explain?
what do you mean by "prorates"?
Alexandre