Unlink Remaining Duration & % Complete

I
Ian Thomson 👤 Member for 22 years 9 months
J
Jaco Stadler 👤 Member for 21 years 10 months

Hi Ian



The Problem with MS is



% Complete = % Time Complete

You Can use % Work Complete

Original Duration in P3 is known as baseline Duration in MS.

And Duration is Actual Duration & Remaining Duration



I Hope this Helps

P
Philip Jonker 👤 Member for 21 years 8 months

Hi there, the autocost thing is in P3. Busy loading MSP at the moment, if I can find something, will reply. Wher are the MSP Fundi’s?

J
Jihad Daniel 👤 Member for 21 years 2 months

Use the Autocost Rules and untick the remaining duration & % complete.