my idea is to visualize the predecessors status in a column, in order to sort the tasks by this predecessors status (first 100% complete, next 0%). On this way, the user could see quickly the work which really can be started.
I am still trying different methods to solve this problem, such as macros Alexandre suggest.
Why are you not trying with Network diagram? I think that will help you to show the progress as well. Only thing you need to filter the required activity.
MS Project does not have such a view that you wish.
It would take a macro to copy predecessor "name" and "%complete" fields in text fields on a specified task row where the resource is working on.
Philip,
MS Project slack is what makes the difference between critical and not critical tasks; I dont understand how a slack zero would make a task being completed: what about not started or not completed critical tasks?
A task is completed if it has a actual finish date or a %complete = 100, as MSP does not distinguish actual finish and %complete.
The normal way to see if an activity is completed, is to look at the float, or slack as referred to in MPS, I do not recall if they have this function. If the slack is blank, the activity is completed
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
some activities may have more than one predecessor,you should think about how to sort by preducessors status.
I think you can save the project as Access database,then do it in ACCESS,it is more powerful than PROJECT for data processing.
Alvaro,
If you want to sort the tasks by their predecessors being completed or not, you would better export data to Excel and finish your work there.
Hasta luego
Thanks all,
my idea is to visualize the predecessors status in a column, in order to sort the tasks by this predecessors status (first 100% complete, next 0%). On this way, the user could see quickly the work which really can be started.
I am still trying different methods to solve this problem, such as macros Alexandre suggest.
Regards.
Álvaro.
Alvaro,
Why are you not trying with Network diagram? I think that will help you to show the progress as well. Only thing you need to filter the required activity.
I still dont understand.
When you set a non-critical task (one with free slack or one with total slack) to 100% complete,
a) the slack remains the same until the 1st successor has started
b) once the 1st successor has started, the slack is 0 (zero)
c) I tried several times with MSP 2002 US, you cannot have a "blank" Slack field, the NULL value is ZERO.
Did you get another result?
I would be interested to know.
I could send my test file to your email address if you want.
Alexandre
Hi, I did not say zero slack, but the slack should be blank, ie no value in the column.
Hi there,
Alvaro,
MS Project does not have such a view that you wish.
It would take a macro to copy predecessor "name" and "%complete" fields in text fields on a specified task row where the resource is working on.
Philip,
MS Project slack is what makes the difference between critical and not critical tasks; I dont understand how a slack zero would make a task being completed: what about not started or not completed critical tasks?
A task is completed if it has a actual finish date or a %complete = 100, as MSP does not distinguish actual finish and %complete.
All the best
The normal way to see if an activity is completed, is to look at the float, or slack as referred to in MPS, I do not recall if they have this function. If the slack is blank, the activity is completed