Can this be done in Project ?

1 reply [Last post]
Forum Guest
User offline. Last seen 19 weeks 1 day ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
I have 3 tasks for 1 resource. 40% of his time he’s on the first task, 40% on the second task and 30% on the third tasks.
The maximum allocation is 80% and the minimum is 70%. How can I make Project level so that it will fill in the missing 20% or 30% ?

Replies

Alex Wong
User offline. Last seen 11 years 36 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Effort is fix

You need to ask for time extension :)