2 weeks of work, so you give them 4 weeks because you don't want to deal with possible 2nd extension- cost? - Can you ask or expect only having to pay for 2 weeks of overhead for 4 weeks of work - for the above reason. Would you be concerned that they agree and then address different legally?
2 weeks of work, so you give them 4 weeks because you don't want to deal with possible 2nd extension- cost?
Forum Sponsor
Top Posters
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
John, without knowing your contract pricing conditions and other circumstances, it's typical that daywork rates is used for additional work and that rates includes overhead, if that so, then 2-weeks extension will be fine...