Its OK. The decision is not yours. Your job is to point out to your management what is the CoC calling for and what you have presented to your client.
I do recommend that you keep track of all this EXTRA work that you are doing, and that you do inform your Boss accordingly that this is EXTRA work according to the Conditions of Contract.
At one point in time, maybe they may decide to collect all this data and send it to the Engineer/ client if they really over do it with asking for extras.
Thanks for your advise. I believe you are correct.
However, my boss told me to follow the instruction of the Engineers..huhuhuhu..I feel bad. Even theres no technical changes done in the program, No dissapproval comment, all are crap comments that i think ENGINEERS seems to hold the approval of the programme to avoid claim for EOT.
First you need to read the Conditions of Contract and then you will find out that the Engineer cant reject. They need to provide a notice to the extent that the Program of Works does not abide by the Contract; scope, time, cost, and quality.
Hence, the Constructability issues (applicable or not) it is up to the Contractor to determine. That is their right because they have studied the Contract in a particular way and they have won the Contract accordingly. It is not up to the Engineer to Reject the Plan.
I would recommend that you send the Engineer a letter refering to clause (14) and what the Engineer responsibilities are. At the same time, stating that you have submitted the Program of Works (several time, I assume) and that the delaying and cost of submmitals will be charged to the Client since this is extra work beyond the scope of the Condition of Contract that the Engineer is asking the Contractor. This will a notice of event taking place (extra cost) and you will submit the total cost of this event as soon as the Engineer stops rejecting the Program of Works. Subsequently, you can calculate the cost of the Planning Engineer/ Project Manager/ Meetings/ Overhead and profit and send it to the Engineer with a copy to the Client.
This should balance your field with the Engineer. At the same time, you need to find someone to review the letters from the Engineer to check if they are over doing their responsibilities and make sure that you get paid for all extras that you are doing.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Dear Mervilyne,
Its OK. The decision is not yours. Your job is to point out to your management what is the CoC calling for and what you have presented to your client.
I do recommend that you keep track of all this EXTRA work that you are doing, and that you do inform your Boss accordingly that this is EXTRA work according to the Conditions of Contract.
At one point in time, maybe they may decide to collect all this data and send it to the Engineer/ client if they really over do it with asking for extras.
With kind regards,
Samer
Dear Samer,
Thanks for your advise. I believe you are correct.
However, my boss told me to follow the instruction of the Engineers..huhuhuhu..I feel bad. Even theres no technical changes done in the program, No dissapproval comment, all are crap comments that i think ENGINEERS seems to hold the approval of the programme to avoid claim for EOT.
Regards,
Dear Mervilyne,
First you need to read the Conditions of Contract and then you will find out that the Engineer cant reject. They need to provide a notice to the extent that the Program of Works does not abide by the Contract; scope, time, cost, and quality.
Hence, the Constructability issues (applicable or not) it is up to the Contractor to determine. That is their right because they have studied the Contract in a particular way and they have won the Contract accordingly. It is not up to the Engineer to Reject the Plan.
I would recommend that you send the Engineer a letter refering to clause (14) and what the Engineer responsibilities are. At the same time, stating that you have submitted the Program of Works (several time, I assume) and that the delaying and cost of submmitals will be charged to the Client since this is extra work beyond the scope of the Condition of Contract that the Engineer is asking the Contractor. This will a notice of event taking place (extra cost) and you will submit the total cost of this event as soon as the Engineer stops rejecting the Program of Works. Subsequently, you can calculate the cost of the Planning Engineer/ Project Manager/ Meetings/ Overhead and profit and send it to the Engineer with a copy to the Client.
This should balance your field with the Engineer. At the same time, you need to find someone to review the letters from the Engineer to check if they are over doing their responsibilities and make sure that you get paid for all extras that you are doing.
With kind regards,
Samer