Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

pre-lim lump sum

2 replies [Last post]
ronron martinez
User offline. Last seen 7 years 32 weeks ago. Offline
Joined: 19 Nov 2009
Posts: 41
Hi, all

as per the prelim, if the clause wouldn’t exercise as per the site condition. The client haven’t right to deduct the clause. based from the prelim lump sum agreement still claimable. please advise

Regard’s
Cy

Replies

Samer Zawaydeh
User offline. Last seen 5 years 25 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Ronron,

Please check your Conditions of Contract and search for priority of documents. Chances are that your client is the party that prepared the Contract Documents and they know it better than you.

Your major documents to search are: Tender, Letter of acceptance, COC particular conditions, BOQ, Drawings, Specifications.

With kind regards,

Samer
Rodel Marasigan
User offline. Last seen 11 weeks 5 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
ronron,
You are looking for EOT with Prolongation Cost. You can Google it and a lot of reference you can use.